Miri-Marudi Road Rehabilitation ahead of schedule with almost 50% of upgrades completed and smooth passage expected during Gawai and Hari Raya Aidilfitri festive holidays
Kuching (Sarawak), Wednesday, 11 April 2018 – Rehabilitation of the 43.2km road connecting Miri to Marudi is progressing well ahead of its original 30-month schedule. By 25 March 2018, the road rehabilitation was scheduled to be 42.87% complete but stands at 49.28% complete – the equivalent of 6.41% ahead of schedule. CMS Roads Sdn Bhd […]